Paving projects will take place this week on portions of Terrell Mill and Windy Hill Road in the Powers Ferry corridor.

The following information was provided by District 2 Cobb Commissioner Bob Ott:

Paper Mill Road Bridge Replacement

  • Paper Mill Road Bridge at Sope Creek is closed through Oct. 25, 2013. The new bridge will include a six foot sidewalk on the south side, providing access to National Park Service trails. A signed detour route (as shown in image) will be provided during construction.
  • Paper Mill Road at Sope Creek  – through Friday, June 21: The contractor will continue bridge demolition and rough grading.

 Indian Hills Parkway at Eastside Elementary School

Find out what's happening in East Cobbwith free, real-time updates from Patch.

  • Indian Hills Parkway – Monday through Friday: Contractor will continue grading, wall construction and placing sidewalks.

Lower Roswell Road Construction

  • Davidson Road to Willow Point Parkway – Monday Friday: This section of Lower Roswell Road is substantially complete except for final striping. 
  • Willow Point Parkway to Timber Ridge Road – Monday through Friday:  Expect periodic lane closures from 9 a.m. to 4 p.m. between Willow Point Parkway and Timber Ridge Road with one lane remaining open. The contractor will be grading, placing concrete and wall construction. Utility relocations should not affect your service. EXPECT DELAYS

Little Willeo Road Sidewalks Construction

Find out what's happening in East Cobbwith free, real-time updates from Patch.

  • Karls Gate Drive to Lake Fjord Pass – Monday through Friday:  Expect intermittent lane closures from 9 a.m. to 4 p.m. with one lane remaining open while the contractor continues wall construction and placing concrete sidewalk. Utility relocations should not affect your service.

Road Resurfacing

Asphalt paving operations are scheduled from Monday through Friday on the following roads. 

  • Terrell Mill Road from Cobb Parkway (US41) to Powers Ferry Road
  • Windy Hill Road from Powers Ferry Road to Wildwood Parkway

One lane will be open at all times. EXPECT DELAYS